Case study

Keeping Hong Kong powered

Hong Kong

Working on electricity pylon after typhoon_Hong Kong.jpg

Client

Undisclosed

Project duration

2010 – 2017

With overhead lines (OHL) forming a major part of the transmission and distribution network, transient voltage dips can be caused by adverse weather conditions such as typhoons and lightning strikes. To mitigate the potential risks of super typhoon damage, a Hong Kong electricity utility commissioned Fugro to help assess the asset integrity of its transmission network, resulting in a strengthening programme to ensure a safe and reliable power supply.The riverbed was geologically complex, so we were tasked with gathering and interpreting additional data to inform design. We also completed a ‘driveability’ assessment to optimise foundation choices.

Life cycle

Planning, feasibility, conceptual design

Design

Construction

Operations and maintenance

Decommissioning

Show full process

Hong Kong has currently 5 power stations, supplying around

0

% of its electricity needs

Hong Kong has a sub-tropical climate and the region can be affected by tropical cyclones between May and November. However, changes in global weather patterns bring an increasing potential for ‘super typhoons’ at a maximum sustained wind speed of 185 km/h or above, with wind gusts of up to 300 km/h.

These super typhoons pose a risk to the region’s overhead lines (OHL). 400 kV towers form the backbone of the transmission network in Hong Kong. If a tower (pylon) is destroyed by a typhoon it can take several months to repair. To counter the potential impact of super typhoons, Fugro was appointed to carry out engineering consultancy services, to assess the asset integrity of a section of the network in Hong Kong and Shenzhen.

Working closely with the structural strengthening design engineers, Fugro provided consultancy services for the planning, design and statutory supervision elements of strengthening of the towers, foundations and slope upgrades.

Services included structural improvements to the steel gantry and cable troughs, integrated geo-structural integrity works and a unique method of strengthening the towers while keeping the structure intact and fully functional during the entire upgrade.

Challenges

The project faced numerous challenges. For example, many of the transmission towers were in remote mountain regions, with no access roads. Also the work had to be completed in sections to minimise downtime on the transmission network.

Future power quality

The historic seven-year project was completed in 2017, helping to ensure that the utility can maintain a safe and reliable electricity supply for Hong Kong and enhance public safety at large.

Moreover, it highlights the need for electricity providers to migrate towards a condition-based maintenance approach that combines predictive and preventive maintenance. Condition monitoring techniques will detect potential fault conditions in advance of failures, making maintenance a proactive process. Under this approach, vegetation management strategies and improvements to asset management processes are essential to ensure exceptional power quality.

The client said: ‘We are grateful to have Fugro’s professional support on this project, which is making our power grids ready to withstand any challenge from the threat of super typhoons.’

Energinet_ROAMES_Transmission_June2022_2.jpeg

Used technology

Fugro ROAMES®

Fugro ROAMES®

Fugro Roames® delivers a powerful 3D real-world environment of your powerline network, enabling you to asses, monitor and maintain your network effectively and efficiently to optimise powerline performance and reduce risk.

MEN03807.jpg

What we do at Fugro

Helping you save time with Geo-data

Find out more