Case study
QuickVision® saves 10 rig days on Shell’s drilling operations
North Sea, UK
Client
Shell UK
Project duration
March 2019 - September 2019
Fugro’s QuickVision® remote-sensing technology enabled real-time conductor well setting from a remotely operated vehicle in the oil and gas field in the UK North Sea. Our vision-based system was used to precisely measure and monitor the height inclination and orientation of nine conductors.
Life cycle
Planning, feasibility, conceptual design
Design
Construction
Operations and maintenance
Decommissioning
Show full process
QuickVision®
Patented vision technology for accurate subsea asset positioning
QuickVision®
The QuickVision® is a patented smart camera that provides accurate subsea asset positioning during drilling and construction support operations to reduce overall time, costs and risks for your project.
Project downtime avoided
days
Challenge
The initial method for achieving such tight tolerances for Shell’s tophole campaign required a bracket to mount a large sensor package with a combined weight of 310 kg onto the conductor.
This approach had many disadvantages:
Required harnessed rig personnel in the moon pool to install the bracket and sensor package onto the conductor
Involved heavy manual lifting
Necessitated overside cover via a local support vessel
Used a heavy sensor package with short battery life
Could not be deployed in marginal weather
Solution
QuickVision®’s unique, vision-based, remote-sensing technology overcame all these issues to facilitate real-time conductor positioning, increase spatial awareness and enhance decision-making.
Our QuickVision® augmented-reality solution enabled the efficient and accurate installation and setting of the 30” conductor low-pressure housing in marginal weather. QuickVision® increases weather capability by reducing or eliminating overside cover, depending on the scope of work: efficiencies resulting from our innovative solution saved Shell an estimated 10 rig days.
Using a remotely operated vehicle (ROV) equipped with a QuickVision® camera, we tracked a unique QuickVision®-coded pattern affixed to each conductor as it was lowered through the water column and into the seabed. This approach ensured we met Shell’s strict tolerance requirements for height, inclination and orientation.
Multiple QuickVision® targets applied to asset for redundancy
The process
First, we fixed a unique QuickVision®-coded pattern onto the conductor, to be carefully surveyed in, to determine its exact position in relation to the conductor’s diameter, length and master slot. We completed this task offshore, onboard the drilling rig contracted to Shell.
Using the QuickVision® camera mounted on the ROV, we followed the conductor on its journey through the water column to the seafloor. Having automatically ‘locked’ onto the pattern in view, QuickVision® accurately tracked the conductors’ positioning, height, inclination and orientation throughout the lowering and cementing stages, eliminating overside cover, which is usually a requirement in marginal conditions but resulted in 10 rig-days saved over all wells in this project.
On the drilling rig, our three-person team monitored key metrics displayed on the QuickVision® dashboard. Shell then used our real-time data to perform any necessary fine-tuning to achieve the precise tolerances required on the well set.
QuickVision® proves its value
Shell was understandably cautious about swapping traditional methods for our cutting-edge technology, so both methods were used in tandem at the first four sites.
However, the fourth location proved a defining moment. As the conductor landed on the seabed, a pin was dislodged on the sensor bracket, rendering the conventional sensor device unreliable. Fortunately, QuickVision® was unaffected, so the conductor setting process continued uninterrupted, using our real-time data to meet Shell’s strict tolerance requirements.
After this event and additional statistical analysis, Shell approved QuickVision® as the primary method for the remainder of the project.
“Collaborating with Fugro to utilise vision technology during drilling operations not only saved time but reduced HSSE exposure among rig personnel. It contributed significantly to Shell’s lift minimisation approach and ensured well set engineering tolerances were achieved.”
Chris Leaf
Geomatics Manager, Shell UK
Innovations
Unique pattern code system negated need for installation of sensor package onto the asset and unnecessary heavy lifting, therefore lowering HSSE risk during installation
Multiple stick-on targets were installed for redundancy on any asset and surveyed in any weather conditions
QuickVision® camera calibration was performed during the ROV’s descent to the seabed
Had all targets been destroyed, measurements could have been taken onscreen using our six augmented-reality tools
Structure position could be tracked in relation to another structure to provide line directions and distance for positioning
QuickVision® enhanced Shell’s and the drilling contractor’s lift minimisation initiative
Overall Shell saved an estimated 10 days on this project
Impact
Reduced HSSE risk; No personnel required in the moonpool or to provide overside cover; No heavy lifting
Accuracy; Precise live monitoring and measurement during lowering and cementing; Positioning, height, inclination and orientation measurements; Fast accurate response to vertical and lateral conductor movement
Enhanced spatial awareness; Augmented reality tools (Inclinometer, Compass Rose, Level Line, Virtual Box, Structure Model, Virtual Buoys and Pattern Tracking); Key metrics displayed on a user-friendly dashboard, updated in real time
Cost-effective approach; All-weather system saved 10 days out of an approximate 120-day campaign; Reduced project complexity;
Saved operational time because patterns were installed offline, not during drilling operations
Related services