Case study

Seafloor cable replacement in the Pentland Firth for SSEN

Pentland Firth, Scotland

Pentland Firth East - Murkel bay beach pull 8.jpg

Client

SSEN (Scottish and Southern Electricity Networks)

Project duration

July 2020 – August 2020

Fugro was tasked with maximising uptime on a project to provide touchdown monitoring and as-laid surveys for Global Marine Group as part of a 37 km, 33 kV power cable replacement for Scottish and Southern Electricity Networks (SSEN) in the Pentland Firth in Scotland, UK.

Life cycle

Planning, feasibility, conceptual design

Design

Construction

Operations and maintenance

Decommissioning

Show full process

Harbour system integration testing with QuickVision 01.jpg

FCV® 600

Harbour system integration testing with QuickVision 01.jpg

FCV® 600

The FCV® 600 is a work-class remotely operated vehicle designed to capture and deliver accurate subsea data and carry out light inspection, repair and maintenace tasks safely and efficiently. 

Operational time on the project

0

Hours

The tracked skid worked well. Considering some sections of the seabed along the route were challenging, to say the least, the WROV remained operational when monitoring the cable touchdown point and in stronger currents than expected.

Jimmy Rodgers

Offshore Vessel Manager, Normand Clipper, Global Marine Group.

Operations

The tracked skid was fully utilised throughout the cable lay operations and logged 355 hours of operational time, of which 190 hours were in currents above 2 knots. Moreover, the tracked skid negotiated the rock-strewn seafloor and traversed inclines of up to 27°.

Innovative highlight

Fugro built the tracked skid WROV system to order for the Pentland Firth project, designing it to suit the FCV® 600 WROVs that support and exceed the demands of deepwater operations. A key design feature was the ability to be launched by a standard LARS with no system modifications; it could also be easily disconnected to allow the WROV to quickly change from tracked skid to free-flying mode, which improved operational efficiency.

Tracked Skid 2.jpg

The compact tracked skid can be quickly attached to the WROV and deployed through a standard A-frame launch-and-recovery system

Impact

The project lasted 15 days, out of which 8 days recorded currents greater than 2.0 knots (1 ms-1). Regular WROVs cannot operate in free-fly mode in such conditions but the tracked skid solution allowed the WROVs to remain operational even in currents over 4.4 knots. In summary, Fugro’s tracked skid solution significantly improved the performance of the WROVs in the Pentland Firth, which resulted in the project being completed ahead of schedule.

Tracked Skid 1.jpg

Tracked skid

FUG 2301 - Windfarm VNR Colour D4 06.jpg

Related services

Operations and maintenance

Find out more